Stay in the know
We’ll send you the latest insights and briefings tailored to your needs
After over a decade of uncertainty, the High Court yesterday reined in the use of the quantum meruit remedy.
A majority of the Court found that builders can no longer seek compensation on a quantum meruit basis in relation to works where the builder has accrued a right to payment under the contract. While builders can commence a claim on a quantum meruit basis for any works performed where the builder has not accrued a right to payment under the contract, the amount claimed cannot exceed the contract price for those works.1
Key Takeaways: what this means for you
|
Peter and Angela Mann (the Appellants) engaged Paterson Constructions Pty Ltd (the Respondent) to construct double-storey townhouses on their property. The contract was a written domestic building contract under the Domestic Building Contracts Act 1995 (Vic) (Domestic Building Contracts Act). Before the completion of the second of the two townhouses, the Appellants asserted that the Respondent had repudiated the contract and purported to terminate the contract. The Respondent alleged this conduct constituted repudiation of the contract.
The Respondent commenced an application in the Victorian Civil and Administrative Tribunal (VCAT), claiming compensation for the fair and reasonable value of works it performed – including works performed in accordance with 42 variations directed by the Appellants.
VCAT found that the Appellants had orally directed 42 variations to the works and that the Appellants’ had repudiated the contract. VCAT ordered the Appellants to pay the sum of $660,526.41.
The Appellants appealed to the Supreme Court and then the Court of Appeal. On each occasion, the Appellants argued that the Respondent was not entitled to compensation on a quantum meruit basis because the Respondent had a contractual claim available.
In the alternative, the Appellants argued that if the Respondent were entitled to compensation on a quantum meruit basis:
Both of the Appellants’ appeals failed.
The Court unanimously upheld the Appellants’ appeal, finding that the Respondent was not entitled to seek compensation on a quantum meruit basis. However, the justification for the conclusion among the Justices differed.
A majority of the Court, consisting of Justices Nettle, Gordon, Edelman and (writing separately) Gageler, held that a builder would not be entitled to claim compensation on a quantum meruit basis in respect of works where the builder had accrued a right to payment under the contract. That is, for example, where the contract works are divided into stages under which the total contract price is apportioned between the stages by specified progress payments.2 The majority did find that a builder could commence a claim on a quantum meruit basis where the builder has not accrued a right to payment under the contract – for example, where payment is not due until the completion of the whole of the works.3 However, the total amount recoverable by a quantum meruit claim, where a contract is terminated for repudiation, is limited to the contract price for the particular stage or portion of the works.4
Justices Nettle, Gordon and Edelman found that there may be circumstances where it is appropriate that a builder recover an amount greater than the contract price, although this would be in exceptional cases only.5 However, this view was not shared by the other Justices.6
The Court unanimously held that section 38 of the Domestic Building Contracts Act excluded the availability of restitutionary relief for variations directed otherwise than in accordance with that section.7 Therefore, the Respondent could not commence a claim for the 42 variations issued by the Appellants on a quantum meruit basis, and was limited to recovering the amounts prescribed by the Domestic Building Contracts Act.
The contents of this publication are for reference purposes only and may not be current as at the date of accessing this publication. They do not constitute legal advice and should not be relied upon as such. Specific legal advice about your specific circumstances should always be sought separately before taking any action based on this publication.
© Herbert Smith Freehills 2025
We’ll send you the latest insights and briefings tailored to your needs