Elaine Naylor & Others v Roamquest Limited and Galliard Construction Limited [2021] EWHC 567 (TCC) concerned a class action brought by leaseholders of a mixed residential and commercial development against the developer/freeholder and contractor. In these proceedings, the Defendants applied to strike out (or for summary judgment to be granted in relation to) the Claimants’ claim for the costs of rectifying potential defects and other losses including for diminution in value.
Factual background
The Claimants were leaseholders of 82 (out of 1,002) apartments in a mixed residential and commercial development known as New Capital Quay in Greenwich, London.
Following testing carried out after the Grenfell Tower fire in 2017, the external envelope of the development was found to lack flame retardant properties and to be non-compliant with applicable Building Regulations. The Claimants therefore brought a claim against the developer/freeholder of the development, Roamquest Limited, and Galliard Construction Limited, who carried out the design and construction.
The Claimants had the benefit of a NHBC Buildmark Policy, which covered the costs of ‘necessary repairs’ (including necessary cladding replacement works) and a waking watch. However, the Claimants sought, among others, the following damages from the Defendants, alleging breach of applicable Building Regulations, breach of contract and breach of statutory duty under the Defective Premises Act 1972:
- Cost of rectifying additional defects detected and/or suspected as being included in the Defendants’ remedial works to the development, including the costs of possible remedial works outside the NHBC policy cover.
- Diminution in value of the Claimants’ flats, calculated as the difference between the purchase price and (alleged) value as at the date of discovery of the defects (i.e. when the presence of non-compliant cladding in the buildings was first confirmed).
The Defendants’ strike out and summary judgment application
The Defendants applied to strike out parts of the Claimants’ claim (or for summary judgment to be granted in relation to the same) on the following basis:
- The additional defects claim was purely speculative in that, among other things, the Claimants had not provided sufficient evidence that the Defendants’ replacement works did or would not comply with Building Regulations.
- The diminution in value claim was presented on an entirely illegitimate basis, and should be based on the value of the flats as at the date of trial when the cladding replacement works would be complete. Further, at such time, there would be no diminution in value as a result of any defective cladding (although there might be residual diminution in value or ‘blight’). The Defendants also noted that the diminution in value claim was duplicative of the Claimants’ claim for speculative additional defects.
- The Claimants did not have standing to bring a claim in respect of the full costs of remedial works for the entire development as they only had a limited interest in the land (whether individually or collectively) and each Claimant’s damages were confined to the extent of their interest. Further, the Claimants’ flats excluded the external parts and main structure of the building, which meant that the Claimants were not entitled to carry out the remedial works, responsibility for which sat instead with the developer/freeholder.
TCC decision
The Court held that the Claimants had an arguable case that they had sufficient standing to bring their claims, including the diminution in value claim. Pending a trial on the evidence, the Court found that it was not in a position to determine these claims on a summary basis or by way of strike out.
As to the Claimants’ additional defects claim, whilst the Court agreed with the Defendants that it was speculative and inadequately particularised, it ordered an adjournment of the Defendants’ application and allowed the Claimants to amend its defects claim so as to plead a proper case.
Analysis
The Court’s decision regarding the Claimants’ additional defects claim is not altogether surprising given that it appears to have been based on ‘assumed’ or ‘potential’ defects and a suspicion that the Defendants’ remedial works, when completed, would be inadequate. Neither perhaps is the Court’s decision in relation to the Claimants’ claim for residual diminution in value given that it was common ground that, as a matter of principle, the Claimants had an arguable claim for the same.
The Court was, however, only required to decide the Defendants’ application for strike out/summary judgment in these proceedings, and the substantive issues of the case remain to be dealt with at trial. In this regard, it will be interesting to see, in particular, how the courts decide to approach the calculation of any diminution in value of the properties affected by combustible cladding – i.e. whether the court will determine that diminution in value should be calculated as the difference between the original purchase price of the relevant property and its subsequent value:
(i) as at the date of discovery of defects (as asserted by the Claimants); or
(ii) when remedial works have been completed (as maintained by the Defendant).
The leading case on residual diminution in value or ‘blight’ is Strange v Westbury Homes (Holdings) Ltd [2009] EWCA Civ 1247. In this case, the Court of Appeal stated that, in principle, a claimant may be awarded damages to reflect a diminution in value if the proper carrying out of remedial works to a property would result in there being a residual diminution in value of the property: suggesting that the assessment of such damages should be conducted on the basis that remediation has been fully completed. The Court of Appeal further emphasised that there must be ‘cogent evidence of a residual diminution in value’, and where both remedial damages and damages for residual diminution in value are awarded, there must be no ‘double counting’.
Based on the principles established in Strange and related authorities, it seems that the Claimants in Naylor will need to overcome a number of significant evidential hurdles in order to bring a successful claim for diminution of value.
Key contacts
Disclaimer
The articles published on this website, current at the dates of publication set out above, are for reference purposes only. They do not constitute legal advice and should not be relied upon as such. Specific legal advice about your specific circumstances should always be sought separately before taking any action.