Follow us

As part of the drive to reach net zero by 2050 and in the lead up to the state election, the Victorian Government has announced plans to legislate the largest renewable energy storage targets in Australia: 2.6 GW by 2030, increasing to 6.3GW by 2035.

Snapshot

  • The Victorian Government has announced plans to legislate a target of 2.6 GW of renewable energy storage capacity by 2030, increasing to 6.3 GW by 2035 (Storage Targets).
  • This target will be facilitated by a $157 million funding package, also announced by the Government on Tuesday, to support the development of batteries and grid forming inverters:
    • $119 million will be invested from the $540 million Renewable Energy Zone Fund in the 125 MW Koorangie Energy Storage System, a big battery and grid forming inverter; and
    • $38.2 million from the Energy Innovation Fund will be invested in four projects using new technology to generate and store clean energy: a battery with grid forming inverter in Terang, a renewable hydrogen electrolyser project in Wollert and two bioenergy projects at farms in Gippsland and Barwon.

Storage Targets

The Victorian Government has announced that the proposed Storage Targets will include both short and long-duration energy storage systems. The intent of this mix is to facilitate a range of services, including shifting load and generation to different times of the day, and also to supply power through longer duration power system imbalances. This provides for a broad range of technologies to be eligible for the Storage Target, including batteries, pumped hydro and hydrogen technologies. The Victorian Government has also referred to grant funding to be provided for ‘seed projects’, indicating that there may be some focus on early stage and R&D technologies.

The Storage Target is proposed to be legislated, with the aim of providing certainty to the market and bring forward investments into energy projects. The policy intent is to provide firm capacity to facilitate the development of new renewable energy projects, and to move Victoria’s energy mix from coal generation to renewable energy.

No further detail about the scheme or legislation underpinning Storage Target has been provided at this point. The Victorian Government has announced that a consultation paper will be released later in 2022 and has called for interested parties to be involved in the consultation[1].

Takeaways

Interested proponents of energy storage projects should continue to monitor as further details of the Storage Target are released, and consider being involved in consultation process.

We will provide further updates and analysis as details of the Storage Target are released.

[1] https://www.energy.vic.gov.au/renewable-energy/a-clean-energy-future/victorian-renewable-energy-and-storage-targets

 

This article was written by Alison Dodd, Partner and Holly McNaughton, Solicitor.

 

For more information, contact:

Alison Dodd photo

Alison Dodd

Partner, Melbourne

Alison Dodd
Heidi Asten photo

Heidi Asten

Partner, Melbourne

Heidi Asten
Neena Aynsley photo

Neena Aynsley

Partner, Melbourne

Neena Aynsley
Nick Baker photo

Nick Baker

Managing Partner, Projects, Energy and Infrastructure, Melbourne

Nick Baker
Gerard Pike photo

Gerard Pike

Partner, Melbourne

Gerard Pike

Key contacts

Alison Dodd photo

Alison Dodd

Partner, Melbourne

Alison Dodd
Heidi Asten photo

Heidi Asten

Partner, Melbourne

Heidi Asten
Neena Aynsley photo

Neena Aynsley

Partner, Melbourne

Neena Aynsley
Nick Baker photo

Nick Baker

Managing Partner, Projects, Energy and Infrastructure, Melbourne

Nick Baker
Gerard Pike photo

Gerard Pike

Partner, Melbourne

Gerard Pike
Alison Dodd Heidi Asten Neena Aynsley Nick Baker Gerard Pike