Stay in the know
We’ll send you the latest insights and briefings tailored to your needs
Over the course of the last 4 to 6 weeks businesses have been incredibly busy dealing with an array of claims from contractors arising out of the COVID-19 pandemic, and the various governmental protection measures put in place to control the virus. For some, the process of reviewing existing contracts and responding to contractor claims has been all consuming, taking up all available time and internal resources. Thankfully, many are nearing the end of this extreme busyness and are beginning to report a return to ‘normal’ (all things considered).
With a return to ‘normal’ comes a returned focus to business as usual; instead of reacting to contractor claims and fighting fires, principals are now finding the bandwidth to recommence stalled negotiations and enter into new contracts. A common question we are being asked as clients return to entering into new contracts is what, if anything, should these new contracts say about the current COVID-19 pandemic? Does the current force majeure provision adequately deal with the pandemic or is something more required?
To assist you to answer these questions, and move forward with confidence in this time of great uncertainty, this article briefly:
A typical force majeure provision generally only applies to excuse performance for events that are unforeseen at the time of entering the contract. As such, they are unlikely, without further amendment, to apply in the current circumstances given the presence of COVID-19 is known.
The absence of a specific provision dealing with COVID-19 leads to uncertainty when the relevant event does arise, forcing reliance on more extreme contractual mechanisms (such as termination for convenience) or less certain common law remedies – such as frustration. This is obviously not ideal and may be problematic for both principals and contractors.
A bespoke clause dealing with COVID-19 allows the parties to identify issues and allocate risk appropriately. It can provide flexibility and increase certainty, both of which are paramount in these turbulent times.
In preparing a bespoke clause which deals with COVID-19, and the consequences if performance of the contract is impeded because of the pandemic, the following issues should be dealt with:
If pricing adjustments are to be provided for, it is important to be clear that any price adjustments should be for tangible costs actually incurred by a party, how the risk of such costs is to be allocated and, where appropriate, should require principal pre-approval of such additional costs. Including an ‘agreement to agree’ on additional costs at a later date may be unenforceable and could expose the parties to lengthy negotiations resulting in unnecessary delay and interruptions to the services or works. Depending on the nature of the transaction, specific costs could include transport increases due to a shortage of commercial flights, limited supply in materials or changes to employee wages due to travel restrictions and a reduced workforce.
Depending on the parties’ commercial position, bargaining power and pricing incentives, a principal may also wish to consider whether it can secure priority of supply to mitigate the impact of the pandemic. For example, if a contractor is working at a reduced production rate, it may be beneficial for a principal to have priority over the contractor’s other customers.
A principal engaging a contractor may also want to include an exception to any exclusive supply obligations imposed by the contract during the COVID-19 event. For example, if:
then the principal may require the option to acquire the relevant goods or services from a third party during the pandemic.
A principal may adopt a two limb approach with the intent of reducing subjectivity when drafting for the cessation of COVID-19 impacts. For example, the earlier of:
Although the second limb still bears a subjective element, its’ risk is mitigated by the fact that, when appropriately drafted, the parties will have a financial interest in being able to perform their normal contractual obligations.
The above is a snapshot of some of the matters that a principal may wish to address in a bespoke COVID-19 provision. However, the exact requirements of such a provision will be dependent on the identities of the parties and their unique circumstances.
Specific COVID-19 drafting encourages companies to continue to stimulate the economy by progressing new projects whilst still offering protection in these challenging times.
The contents of this publication are for reference purposes only and may not be current as at the date of accessing this publication. They do not constitute legal advice and should not be relied upon as such. Specific legal advice about your specific circumstances should always be sought separately before taking any action based on this publication.
© Herbert Smith Freehills 2024
We’ll send you the latest insights and briefings tailored to your needs