Extensions of time - the starting point
On 10 February 2017, the Court of Appeal released its decision in the case of Carillion Construction Limited v Emcor Engineering Services Limited and …
30 January 2017
Design liability under the NEC form of contract
In SSE Generation Limited v Hochtief Solutions AG and another decided on 21st December 2016, the Court of Session in Scotland considered a contractor's …